Geotechnical Investigation of 100MW Hydropower Project

Geotechnical Investigation of 100MW Hydropower Project 2018-03-22T14:37:42+00:00

Geotechnical Investigation of 100MW Gulpur  Hydropower Project At Kotli AJK

Scope:

  • Drilling of boreholes, 785 meters drilling at 14 locations, up to 125m max. depth.
  • Standard Penetration Tests
  • Undisturbed / Disturbed sampling
  • Seismic Refraction
  • Resistivity Survey
  • Detail Mapping
  • Water Pressure Packer Test in Rock
  • Grouting Test
  • Elastometer Test (to compute Deformation & Elastic Modulus of in Situ Rock)
  • Laboratory Testing

Project Details

Year of Execution
2014