DECON & PINGGAO Group Completed and Operated Two Grid Stations of FESCO Successfully

Firm DECON International Pvt. Ltd., as a Subcontractor of PINGGAO Group Co., Ltd, China in ADB-Trench-III-FESCO-02, operated and completed 132kV Athara Hazari Grid Station and 132kV Garh Mahraja Grid Station successfully. DECON also provided Project Management services to PINGGAO, for managing the entire construction of 132kV Grid Stations. Project Management & Civil Work of Procurement of Plant, Design, Supply and Installation for Conversion from 66kV to 132kV Air Insulated Switchgear (AIS) included following scope;

  1. Topographic Survey
  2. Geotechnical Investigations
  3. Design of Grid Stations (Civil + Electrical)
  4. Civil Works for Switchyard
  5. Control House Building
  6. Pavements + Drainage
  7. Electro-Mechanical Works
  8. Testing & Commissioning

DECON delivered exceptional performance in completing the project. This marks a major step forward in electricity transmission in Faisalabad.

https://youtu.be/Hl35MXc0Nis

By | 2018-10-08T06:31:39+00:00 October 8th, 2018|Construction, Engineering|